City Managers Meeting
Attendance:
City: City Manager – Steve LeBlanc; Director of Public Works* – Brandon Wade; Police Chief - Ken Mack
WGIPOA: Tom Boothe, Tom Grace, Patti LeClear, Wanda Greer, Jerry Mohn
*Brandon Wade had several members of the Public Works Department in attendance for a better understanding of the issues and concerns expressed by Chamber members. The members included: Angelo Grasso – Senior Assistant Director; Eric Wilson – Assistant Director of Utilities; Keith Stovall – Street Maintenance and Traffic; Mike Dricks – Public Works Special Events and Traffic Manager
Topics of Discussion
Department of Public Works
Response: It is a TEXDOT issue and Angelo will send an Email to the area Supervisor, Bill Babbington, to mow the area.
Response: The City will investigate and they would like to know the specific location Sands of Kahala would like the light.
Response: This is a Planning Department issue and Brandon will check it out.
Response: The sewers are under design for the area. The bonds for construction will probably be let in February, 2008. If there are not any problems with easements, it could take possibly one year to install and build out.
Response: The streets will be paved when the sewer lines are completed. It is not economically beneficial to do the roads now, and then tear them up when the sewers are constructed, and then pave the roads again. Brandon, however, will see that the current pot holes are patched.
Response: The City does not mow the ditches in front of people’s homes. It is the responsibility of the homeowner to mow the ditches or have the home owners association hire someone to mow.
Response: Brando assigned the work to be done.
Response: City Council approved the study last week and the project will take 6 months to complete.
Response: The City will do as soon as possible. This has a very high priority and they will fit it into a schedule.
Response: The City will pursue and Brandon also suggested to contact David Murphy of CenterPoint Energy. J. Mohn gave the information to Mr. Murphy at the Saturday WGIPOA meeting.
Response: Brandon was hopeful that all is necessary is a preliminary engineering work. However, he did mention this could lead to something more substantial. It was also indicated that the outfall ditches are actually higher than the ditches running to them and this is a problem.
Response: City Council approved the study last week and the project will take 6 months to complete. There is a concern about the piped in ditches in Palm Beach. To make it drain properly, the City may have to remove the pipes all along the frontage area. A pump station here may also be necessary.
Response: The city will prepare and install the sign after Fat Tuesday, 2/20. This will be done by Keith Stovall and Mike Dricks.
Response: The City is ready to advertise for bids as soon as an easement is completed. It is a critical one and all the City needs is a 10 foot utility easement. The delay is from the property owner who is not eager to grant the easement. The price keeps going up from a token value to an appraised value. The owner also would like all fees waived and other expenses. The plans are 100% ready
Response: The construction is not finished and when it is done, the landscape will be replaced and brought back. The new plant is now in operation. The old plant, "the Green Monster", is going away and no need to worry about the landscaping.
Response: The catalyst in getting sewers and projects for this area is the Sweetwater Development at the north end of 8 mile road. The development’s infrastructure will be financed through a PID (Public Improvement District) and this should be approved by City Council the first week of March. There will be a lift station that will force the main and water lines to Stewart Road lift station. The new lift station, which is under design, will also handle the Sportsman Road area as well. All the homes will have to have grinder pumps. The question was raised by the President of the Sportsman Road Association who to contact on grinders at the City and that is Eric Wilson.
Response: The City will go out to inspect the bridge and do an assessment.
Response: Keith Stovall will go out and investigate to determine what is necessary for a preventative maintenance program.
Response: Brandon will request the LAN engineering firm to determine the costs in elevating the road by 6 inches.
Response: The standing water is not caused by the new sewer water line but mainly from the topography. Hopefully, a lot of this will be resolved when FM 3005 is elevated and proper outfall ditches, culverts, and drains are constructed. The drainage along FM 3005 is a TEXDOT responsibility.
Response: A study is required and part of the engineering design work is currently underway. The need is to figure out where the drainage outfall is and to re-grade the ditches. Angelo mentioned the low point of the roadway is from the west end of the subdivision. In addition, the pipes in the subdivision vary from 18 inches to 8 inches and very difficult for the water to drain properly. Now, west and east drain to 16 mile road and the low point is the west side and drains to the east and all to the 8 inch pipe, which cannot handle any heavy flow. In addition, pipes under the driveways are a problem, because in some the high point is the middle of the driveway and the low point is the other end and the difference could be one foot in elevation. The water cannot possibly drain adequately in these areas. The City is spending time in evaluating the drainage and the engineering work will have specific recommendations to hopefully resolve the problem.
Response: To obtain longer hoses and bigger pumps will cost in excess of $15,000 and City Council will have to approve. Brandon will request approval
Response: It is underway and should be completed in 6 months.
Response: Target is in the year 2008 but depends on the outcome of the engineering study that is currently underway.
Response: The cost will be $350 to tap the sewer line. There will also be a cost to pump and clean out the septic tank. There are several firms that perform this service and the property owners need to negotiate the best value. It will also require a plumbing permit.
Response: The City has a concern about the private streets in Acapulco Village and liability issues when the sewers are installed. Brandon advised the City will pursue and talk to the property owners. The engineering phase for installation of the sewers is under the design phase now.
Response: The City plans to widen 11 mile road and they need an easement from the owner. For mitigation, the City is willing to let the owner use the land under the Sunny Beach water tank. To get the easement then, the water tank will have to be demolished and come out soonest.
Response: The City has already requested CenterPoint Energy and will do again. J. Mohn gave the information to Mr. Murphy at the Saturday WGIPOA meeting.
Response: The City will advise CenterPoint Energy to be re-grading the road shoulders. J. Mohn gave the information to Mr. Murphy at the Saturday WGIPOA meeting.
Department of Public Safety
Response: The Chief will get with Public Works to install the bollards and that adequate signage is placed in the area. It was later pointed out that the bollards have already been replaced.
Response: There is an ordinance that allows horses on the beaches in the west end from Memorial Day through Labor Day from 9:00 AM in the morning to 8:00 PM at night, except Memorial Day, July 4, and Labor Day. Between 7.5 and 9 mile road, horses are allowed year around. The stipulation is the horses cannot cross any sand dunes. There are no requirements on the speed.
Response: There are at least three officers each shift (3 per day) including a sergeant. The Chief advised there are still 30 openings in the police force but there are 12 new officers finishing up in the training academy that will be added soon. The west end is adequately covered now, especially with all the new development.
Response: Brandon will request the Compliance Officer to make patrols of this area at least every two weeks. The Chief will advise the police officers to patrol this area more effectively.
Response: Contact Officer Gordon Morse at 682-3603 or Lt. Tors in the Police Department.
Response: The Chief mentioned it will not be necessary for an officer to be at the former MUD 1 building because all the patrol cars will be equipped with a laptop computer. The laptops have been purchased and being phased in now into the patrol cars and should be complete by the end of the year. This will enable the officer to fill reports immediately and to be on the road most of the time patrolling an area. As far as taking calls, everything goes through the dispatch.
Brandon mentioned that the MUD 1 Building is now open 8:00 AM to 5:00 PM and it is capable in taking water bill payments. They cannot make change but will take cash. They cannot take credit cards yet. If there is any problem with water or trash to call: 737-2778.